Baptistcare Five Dock

Baptistcare Five Dock

Client: Lendlease
Asset Owner: BaptistCare


Project description

The Principal Contractor (Lendlease Building) was engaged by BaptistCare (NSW) to design and construct affordable housing across several sites in NSW under a NSW Government Initiative. Our project scope comprised of the supply, excavation, installation and certification of new infrastructure services between Great North Road and the new building in Kings Rd in Five Dock, within The Inner West Sydney.

This included upgrading:

  • Potable water supply
  • Stormwater drainage
  • High voltage power cables
  • Pavement works

Design and construction costs for the total project was budgeted at $23m

Plant type

5 & 13t Excavators, Combo Jet Vac Truck, Skip truck, 5t Tipper Truck,

Pipe size & length

115m x DN150 DICL water main

90m x DN375 RCP Stormwater pipes

11 kV High voltage cables

Design and build dates

Mar 2017- Late 2019

Project value

$1.4 million

Roles and responsibilities

Killard – Construct, rehabilitate, asset relocation, condition assessment

Stakeholder liaison

By Project Management Personnel

Safety and environment

Safety incidents – nil

Environmental incidents – nil

Client referees

Mr. Ben Samcou

Lendlease

Relevance

This project demonstrated our ability as a civil construction company to conduct multifaceted infrastructure works in a dense urban environment at night and in part, on a RMS road.

Furthermore, we exhibited our commitment to quality, environment and WHS by meeting the subcontractor trade specific requirements of Lendlease.

The general trade requirements also included the submission of relevant Council Road and Footpath Applications, Work Zone Applications, RMS Applications, ROL permits as well as community liaison, materials handling, noise, dust and traffic control measures.